.17th March 2008 |
Les Rivieres, Montourtier, Mayenne |
. |
| Bedroom One, as it was, now fitted with ensuite bathroom is now finished. Ensuite Size 9' 0" by 10' 0" approx. Work got started on the 8th January, progress so far :- Works external to Bathroom Connection to Fosse Septic via 100mm and 40mm pipes should be completed by 16th Jan. This work entails 20 metres of 100mm & 10 metres of 40mm pipe, installed underground, up and along the house wall, through a 300mm stone wall (two holes for 100 & 40mm pipe) at a height of 6 metres to reach the proposed ensuite. Now awaits connection to the various bathroom items. Access from Bedroom to new Ensuite to Start 18th Jan. Access now completed, 22nd Jan.
Within New Bathroom Re routing of heating system and electrics, repairs to floor due to start 24th Jan. 3rd Feb, Floor, Heating system re routed, Wall studding 75% complete, consumer unit installed. Installation of electrics started. Installation of Velux window and roof vent yet to start. Watch this space..... To be fitted out with, Toilet, Sink and Shower. .
| ||
Weekly Report Going up the new stairs
3rd February, most of the studding is completed, coming week should see walls plaster boarded, Velux/ventalation installed and electrics progressing to a more finished state. Some of this work depends on the weather and at present forecast not good.
Views from above window
Three views from the new velux window installed in the new ensuite bathroom. 20th February 2008
Light, under stairs.
Left of door, centre cross beam to be remove, to fit shower, ceiling plaster board fitted.
Electrics, all runs done, connections finished as Plaster boarding is finished by Wednesday, 11th March.
Plasterer due on Monday 17th March, arrived 10:30am
Opposite sink area plastered, below toilet area part done
Re-started June
Above, shows toilet and sink areas and below where the shower will be located. Photos 9th June 2008,
June the tiling completed and cold & hot cold water pipework finished up to rear of walls for Shower, Sink and Toilet. A cold water filter system also installed which is now in use on all hot water taps in the house and cold water supply to the new ensuite. French water in this area is chalky and needs to be filtered before use. Target, to have flooring cork tiles, sink and toilet in operation by 16th June. Shower to be fitted later and painting to be done when no visitors around with paint from UK.
Toilet & Sink were in operation on the 16th as planned. The cork tiles 11m2 in area, took 5.5ltrs of yatch varnish to get to the required finish, this took five days to do, waiting for each coat dry before applying the next coat. (Varnish cost 100 euros approx) Toilet & sink were instaled within the day. (S & T cost 120 euros approx)
Details of Shower now installed and working:15th September 2008 Shower cabinet by OCL model 'Pompei' is a hydromassage shower. It as four different shower settings, overhead, personal, seated body, standing body. Also fitted is a radio, extraction fan, two lights. Size 210 x 90 cm approx.
Views of 'The Shower' 1. view of outside. 2. view of controls. 3. view through shower looking towards sink and toilet.
|
|